Payra power plant is a 1,320MW ultra-supercritical coal fired with two power generating units at Dhankhali, in the Patuakhali district of Bangladesh, approximately 235km away from Dhakar. It is the first power plant to come online, among a series of new thermal power projects being developed across the country as part of Bangladesh’s plan to increase its electricity generation capacity from 10,445MW to 24,000MW. The Consortium FINT-C3 (Ferbeck International SA and C3 Chimney Consultants and Construction Co., Ltd.) has been awarded an EPC contract of a 220 meter-high-concrete chimney by NEPC.

BCPCL awarded the EPC contract for the power plant to a Chinese consortium comprising China Energy Engineering Group Northeast No. 1 Electric Power Construction (NEPC), in March 2016.

ABOUT THE PLANT

  • Type of plant
    2x660MW ultra-supercritical coal fired power plant
  • Owner
    Joint Venture Bangladesh-China Power Company (BCPCL)
  • Contractor
    China Energy Group Northeast No.1 Electric Power Construction Co., Ltd. (NEPC)

ABOUT THE CHIMNEY

  • Year
    Completed in 2020
  • Shape
    Bottom conical to top cylindrical shape
  • Height
    220m
  • Outer Ø
    24m (bottom), 18.3m (top)
  • Liners
    2 carbon steel liners, Ø = 6,500mm each with borosilicate protection

A part of


www.ferbeckinternational.com
Legal Notice | Privacy Policy | Site map

WSF © 2019 -

LISBON

Headquarter

  • Av. D. João II, nº 45

  • 3rd Floor, 1990-084

  • Lisbon, Portugal

  • +351 218 429 270

JAKARTA

Indonesian Branch

  • L'Avenue Office Building

  • Jl. Raya Pasar Minggu Kav 16 Pancoran

  • Jakarta Selatan, Indonesia

  • +62 21 8066 7250

DHAKA

Bangladesh Branch

  • Kha-48/B Pragati Sarani

  • Shahjadpur, Gulshan

  • Dhaka-1212, Bangladesh

  • +880 2 55048009