Jawa 9&10
Indonesia

Jawa 9 and 10 are two power plant units that is developed as an expansion of the existing Suralaya coal-fired steam power plant located in Pulomerak District, Cilegon, Banten, Indonesia. Each unit will have a capacity of 1GW each.

To meet the domestic electricity demand, the country is expected to require the development of more than 290 power plants. The Jawa 9 and 10 power plants are part of the plans to fulfil this demand. The project is owned by PT PLN, a national electricity utility owned by the Indonesian government. PT Hutama Karya is in charge of the engineering, procurement, and construction (EPC).

FERBECK INTERNATIONAL SA has been awarded an EPC contract for one 266.5 meters-height concrete chimney by PT Hutama Karya, Indonesia.

ABOUT THE PLANT

  • Type of plant
    2x1000MW ultra-supercritical coal-fired power plant
  • Owner
    PLN Indonesia
  • Contractor
    PT Hutama Karya, Indonesia

ABOUT THE STACK

  • Year
    2020–ongoing
  • Type of structure
    Concrete chimney
  • Height
    266.5m
  • Ø
    8,5m
  • Liners
    2 carbon steel liners with borosilicate

A part of


www.ferbeckinternational.com
Legal Notice | Privacy Policy | Site map

WSF © 2019 -

LISBON

Headquarter

  • Av. D. João II, nº 45

  • 3rd Floor, 1990-084

  • Lisbon, Portugal

  • +351 218 429 270

JAKARTA

Indonesian Branch

  • L'Avenue Office Building

  • Jl. Raya Pasar Minggu Kav 16 Pancoran

  • Jakarta Selatan, Indonesia

  • +62 21 8066 7250

DHAKA

Bangladesh Branch

  • Kha-48/B Pragati Sarani

  • Shahjadpur, Gulshan

  • Dhaka-1212, Bangladesh

  • +880 2 55048009